Chile loads its copper cannon with 13 projects for a bullish 2026

Collahuasi C20+ project will extend the mine’s life by 20 years. (Image courtesy of Anglo American.)

Thirteen Chilean copper projects worth $14.8 billion are expected to hit key milestones in 2026 as prices rise on fears of a global supply squeeze.

Chile stands to benefit as seven domestic projects aim to start operations next year, adding almost 500,000 tonnes of annual capacity backed by $7.1 billion in investment, according to official figures.

The list includes Anglo American/Glencore’s Collahuasi infrastructure and productivity upgrades, known as project C20+, Codelco’s Rajo Inca structural project, Capstone Copper’s Mantos Blancos and Andes Iron’s debated Dominga.

Another six developments plan to begin construction, representing $7.7 billion in spending tied to copper’s strategic role in energy and technology. Those include BHP’s Spence and Capstone’s Santo Domingo.

Juan Ignacio Guzmán, CEO of Chilean mining consultancy GEM, said that while several projects are scheduled to begin producing in 2026, they won’t achieve full ramp-up immediately. Based on estimates from the Chilean copper commission (Cochilco) Guzmán noted the pipeline could lift Chile’s output to about 5.6 million tonnes, or roughly an additional 100,000 tonnes of fine copper within a year. 

The analyst said the International Copper Study Group sees a 2026 deficit of 150,000 tonnes, a gap that would widen if Chilean projects stall.

“The long-term reality is that building a new mine is difficult. Nearly everything the global economy wants to invest in is copper-intensive, including the energy transition and AI,” Benchmark Minerals copper analyst Albert Mackenzie said. 

Guzmán said the main risk for Chile’s 2026 slate lies with community relations rather than market dynamics or the new government taking office in March 2026.

“The role of communities will continue to be relevant,” he said. While projects starting operations have already cleared key hurdles, he warned that those set to begin construction face ongoing approval processes that could end up in court.

The consultant also highlights that significant investment is essential for these projections to materialize. State-run Cochilco expects the country to attract $105 billion from this year through 2034. The agency notes the estimate includes expansions at consolidated operations such as BHP’s (ASX: BHP) Escondida, the world’s largest copper mine.

Katz factor

The recent victory of ultra-conservative former congressman José Antonio Kast, who is set to take office as Chile’s next president in March, is being viewed by markets as positive. Kast’s win represents a shift toward a more pro-investment, pro-development stance in Chile, mining investors said.

His administration is expected to streamline permitting and environmental approvals, reduce regulatory uncertainty and offer greater fiscal stability, lowering the risk of new tax or royalty changes mid-cycle.

Kast’s law-and-order approach could also bring greater operational certainty by curbing protests and disruptions that have delayed mining activity in recent years, though it may raise tensions with some local communities, industry insiders noted.

For Chile’s 13 copper projects, some of which are nearing production, this could translate into faster decision-making, easier access to private and foreign capital, and a higher likelihood of moving from planning to execution in time to capture a bullish 2026 copper market.

Record highs

Copper has climbed nearly 40% this year, hitting a record $11,800.5 a tonne on Dec.11 as supply concerns deepen. Stockpiling in the US has added strain, with companies accelerating cathode shipments into American warehouses ahead of possible 2027 tariffs on refined copper.

Mackenzie said the US has driven the 2025 price run-up, with an estimated 730,000 to 830,000 tonnes diverted into domestic storage and leveraged against the CME futures curve. The shift has tightened LME inventories, raised premiums in Europe and Asia, and boosted prices for CME-deliverable brands such as Codelco cathodes.

Check live copper prices

Sentiment also strengthened after Chinese smelters announced a 10% output cut for next year. JP Morgan expects a 2026 refined copper deficit of 330,000 tonnes. Mackenzie said mining capacity will be tight because no major new expansions are coming online and several operations are underperforming. Even when new mines open, he said, metal takes time to reach the market.

“When Freeport’s Grasberg mine had its disruption, prices jumped immediately,” he said. “Traders didn’t say, ‘let’s wait three months for it to matter.’”

The market “finds a way

Mackenzie dismissed long-term structural deficit forecasts. “The market always finds a way,” he said. Higher prices can curb demand, more scrap can enter the system and substitution can ease pressure. He acknowledged, though, that demand will rise and extraction is getting harder. 

Projects needed to meet that demand should already be under construction, and some buyers are now exploring alternatives after years of bullish shortage narratives.

Comments

Your email address will not be published. Required fields are marked *

No comments found.

{{ commodity.name }}

Contest Ranking Modal BG Contest Ranking Modal BG
Contest Ranking Title

The new Mining Power Rankings are live. Vote for the sector’s leaders in each of the Large-, Small-, and Micro-Cap leagues.

Vote Now