Lead, South Dakota--(Newsfile Corp. - December 18, 2025) - Dakota Gold Corp. (NYSE American: DC) ("Dakota Gold" or the "Company") is providing an update on the metallurgical testing program (the "Met Program") designed to inform the Feasibility Study ("FS") at the Richmond Hill Oxide Heap Leach Gold Project ("Richmond Hill" or the "Project").
The FS Met Program is scheduled for completion in Q3 2026 with staged testing and milestone reporting throughout. Extensive metallurgical drilling was completed in 2025 (Map 1) and the Company expects to ship 4,000 kg of material to Forte Dynamics Lab (the "Lab") that represent 28 potential geo-metallurgical domains, and complete more than 30 column tests. To date, the Company has received results for two initial composites from the MW3 zone in the northern part of the property.
Highlights from this update:
"The FS and Met Program represent an important step in the evaluation and de-risking process for Richmond Hill. Historical metallurgical tests exhibited variability in column recoveries, and similar variability is anticipated in the current Program. The results are consistent with my experience with comparable heap leach gold deposits and support the potential for low-cost leach heap processing as envisioned in our July IACF. Over the next 12 months, we will finalize our FS metallurgical testing and trade-off studies to support the FS and to inform future permitting activities," said Jack Henris, President and COO of Dakota Gold.
Project leverage to Gold Prices and Recovery
Richmond Hill exhibits strong leverage to increasing gold prices. The Initial Assessment with Cash Flow ("IACF") published in July 2025 demonstrates that at gold prices exceeding $4,000 per ounce and at various ultimate gold recovery scenarios, the Project NPV5% can be in excess of $4 billion.
"I'm very excited to be part of the team that is advancing the Richmond Hill gold project towards a potential multi-billion NPV opportunity, in possibly the best gold price environments we've seen in decades. We will continue to advance the Project with urgency as we work towards production in 2029," said Shawn Campbell, CFO of Dakota Gold.
Table 1 – IACF; After-tax NPV5% Measured, Indicated and Inferred mine plan sensitivity to gold recovery
| Gold Recovery | |||||
| 68.3% | 72.6% | 76.9% | 81.1% | 85.4% | |
| Gold Price | NPV5% in US$ Million | ||||
| $2,350 | $1,389 | $1,571 | $1,752 | $1,932 | $2,113 |
| $2,750 | $1,915 | $2,127 | $2,338 | $2,549 | $2,761 |
| $3,150 | $2,439 | $2,682 | $2,924 | $3,167 | $3,409 |
| $3,550 | $2,964 | $3,237 | $3,511 | $3,784 | $4,057 |
| $3,950 | $3,488 | $3,792 | $4,096 | $4,401 | $4,705 |
| $4,150 | $3,750 | $4,070 | $4,389 | $4,709 | $5,029 |
Metallurgical Program
The scope of work to complete the FS study includes ore characterization; column leach testing; comminution and crushing studies; process optimization and recovery; and deleterious elements and environmental testing. The Company has shipped approximately 10% of the material to the Lab to date and continues to assemble material for composite testing. The test work is being informed by the results to date as well as the historical work at Richmond Hill.
Samples from 12 drill holes from the Company's 2025 drill campaign were composited for the current MW3 zone tests. Two columns of material grading 0.96 g/t Au were tested at a 1" and 0.5" crush size. The recoveries for those columns were 61% and 64.8%, respectively. Two columns of material grading 0.53 g/t Au were tested at a 0.75" and 0.5" crush size and the recoveries for those columns were 61.6%, and 64.8%, respectively. The FS metallurgical program will include analysis to understand whether either encapsulation or minerology impacted ultimate recovery.
Characterization results announced today from the M3W zone material did not contain preg-robbing material. Additionally, based on QEMSCAN and ICP-OES, the material did not identify any deleterious elements or mineralogy. These results will guide future trade-off studies on the requirement for agglomeration.
The Richmond Hill historical feasibility study was conducted by several labs as part of the metallurgical program to construct and operate the historic Richmond Hill mine. The 51-column tests that were performed, had a wide range of recovery in the column work, however, the sub-set once classified as oxides had an average recovery of 89% (Appendix A-B). The historical Richmond Hill metallurgical data does not detail the process for classifying the 31-column material as oxide ore. In addition, regionally, Coeur Mining discloses variable recoveries from 71% to 80% in the Wharf Mine Operations, South Dakota Technical Report Summary dated December 31, 2021.
Map 1 – Location of historical heap leach samples and 2025 metallurgical drill holes
To view an enhanced version of this graphic, please visit:https://images.newsfilecorp.com/files/8218/278564_cef71495a4a70a46_002full.jpg
About Dakota Gold Corp.
Dakota Gold is expanding the legacy of the 145-year-old Homestake Gold Mining District by advancing the Richmond Hill Oxide Heap Leach Gold Project to commercial production as soon as 2029, and outlining a high-grade underground gold resource at the Maitland Gold Project, both located on private land in South Dakota.
Subscribe to Dakota Gold's e-mail list at www.dakotagoldcorp.com to receive the latest news and other Company updates.
Shareholder and Investor Inquiries
For more information, please contact:
Jack HenrisPresident and COOTel: +1 605-717-2540
Shawn Campbell Chief Financial OfficerTel: +1 778-655-9638
Carling GazeVP of Investor Relations and Corporate CommunicationsTel: +1 605-679-7429Email: [email protected]
Qualified Person and S-K 1300 Disclosure
James M. Berry, a Registered Member of SME and Vice President of Exploration of Dakota Gold Corp., is the Company's designated qualified person (as defined in Subpart 1300 of Regulation S-K) for this news release and has reviewed and approved its scientific and technical content.
Quality Assurance/Quality Control consists of regular insertion of certified reference materials, duplicate samples, and blanks into the sample stream. Samples are submitted to the ALS Geochemistry sample preparation facility in Winnipeg, Manitoba. Gold and multi-element analyses are performed at the ALS Geochemistry laboratory in Vancouver, British Columbia. ALS Minerals is an ISO/IEC 17025:2017 accredited lab. Check samples are submitted to Bureau Veritas, Vancouver B.C. as an umpire laboratory. Assay results are reviewed, and discrepancies are investigated prior to incorporation into the Company database.
Forward-Looking Statements
This communication contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. When used in this communication, the words "plan," "target," "anticipate," "believe," "estimate," "intend," "potential," "will" and "expect" and similar expressions are intended to identify such forward-looking statements. Any express or implied statements contained in this communication that are not statements of historical fact may be deemed to be forward-looking statements, including, without limitation: our expectations regarding additional drilling, metallurgy and modeling; our expectations for the improvement and growth of the mineral resources and potential for conversion of mineral resources into reserves; completion of a feasibility study, and/or permitting; our expectations regarding free cash flow and future financing, and our overall expectation for the possibility of near-term production at the Richmond Hill project. These forward-looking statements are based on assumptions and expectations that may not be realized and are inherently subject to numerous risks and uncertainties, which could cause actual results to differ materially from these statements. These risks and uncertainties include, among others: the execution and timing of our planned exploration activities; our use and evaluation of historic data; our ability to achieve our strategic goals; the state of the economy and financial markets generally and the effect on our industry; and the market for our common stock. The foregoing list is not exhaustive. For additional information regarding factors that may cause actual results to differ materially from those indicated in our forward-looking statements, we refer you to the risk factors included in Item 1A of the Company's Annual Report on Form 10-K for the fiscal year ended December 31, 2024, as updated by annual, quarterly and current reports that we file with the SEC, which are available at www.sec.gov. We caution investors not to place undue reliance on the forward-looking statements contained in this communication. These statements speak only as of the date of this communication, and we undertake no obligation to update or revise these statements, whether as a result of new information, future events or otherwise, except as may be required by law. We do not give any assurance that we will achieve our expectations.
All references to "$" in this communication are to U.S. dollars unless otherwise stated.
Appendix A - Historic Richmond Hill oxide metallurgical column test work by St. Joe
To view an enhanced version of this graphic, please visit:https://images.newsfilecorp.com/files/8218/278564_cef71495a4a70a46_003full.jpg
Appendix B - Historic Richmond Hill metallurgical all column test work by St. Joe with red circle showing initial column results for M3W compositeTo view an enhanced version of this graphic, please visit:https://images.newsfilecorp.com/files/8218/278564_cef71495a4a70a46_004full.jpg
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/278564
The new Mining Power Rankings are live. Vote for the sector’s leaders in each of the Large-, Small-, and Micro-Cap leagues.